Renovation proposal 67 Hunter Street, Euroa

risk_register

Risk register

Severity-by-likelihood table for the proposed work, with mitigations and owners.

# Risk register — 67 Hunter Street, Euroa

> Lorem ipsum. Stub document body; the real version is generated by the
> orchestrator Worker and stored in R2.

| Risk | Severity | Likelihood | Mitigation | Owner |
| --- | --- | --- | --- | --- |
| Weather delay to exterior paint | Med | Med | Build a 1-week weather buffer into the schedule. | Owner |
| Splashback substrate replastering | Med | Med | Allow 1 day tiler visit with replastering as a contingent line. | Tiler |
| Tapware delivery slip | Med | Low | Order at week 0; 3-week lead time. | Owner |
| Native grass strike rate | Low | Med | Overseed at week 6; expect 90% strike at week 10. | Gardener |
| Furniture removal cost overrun | Low | Low | Owner clears interior furniture the week before work starts. | Owner |
| Heritage overlay mis-read | High | Low | Confirmed in compliance document; not in a registered overlay. | Owner |